After reading the good reports on recycled plastic posts for track support, I bought a batch of 80mmx80mm posts from Filcris.
Until yesterday, they were stored in the shade but I then began drill post holes and place several across the lawn (some are in shade, some semi-shade and the remainder in full Sun).
After a couple of hours of full Sun, those not shaded have become "banana" shaped.
Probelem appears to be uneven expansion.
The side facing the Sun expands, whereas shaded side does not!
Turn a post around and it begins to twist the opposite way ; place it in the shade and it eventually resumes original shape.
Have phoned Filcris but got the answering machine, so have sent an email.
Anyone else experiencing similar problems with these posts?
They apparently did a roaring trade at the Peterborough Show and "sold out", so there must be a lot others experiencing (or about to experience) a similar scenario!
John.
Chris from Filcris phoned in response to email and offered (unprompted) to collect posts and issue a full refund.
He confirmed these posts are susceptible to uneven expansion and not suitable for all applications.
I told him I may keep them for use in shaded areas of the garden (in particular supports for the terminal stations where they will be protected from Sun).
Situation was left that I would notify him of my decision and he would uplift and issue refund for some or all of the posts if I decide I do not want them.
Five Stars to Filcris for "customer care" but let this be a cautionary tale for others contemplating a "plastic" solution.
John.
P.S. Thank God I didn't fix the posts and lay track in the cooler weather or I would have faced the horror of a twisted railway and the problem of digging out posts set in concrete!
Would have loved to have seen the photos John!!!
Ian
Well I have set up Filcris products in my garden & must say that 50% is on the ground & 50% is on elevated.
The elevated will heat up more readily than the ground based material which seems more stable.
All my posts have been in the ground for over a year now & have had sub zero winter & summer heat extremes. None of my posts have bent like bananas. None of my posts are set in concrete they are just driven into the ground (about 2 feet) . Part of the elevated section has been backfilled with rubble & topsoil to be ground level. All my track is GRS brass on the plastic boards. The extremes of temperature with brass & plastic seems to be a workable combination.
Frosty nights followed by full (GB East Midlands) sunshine. The brass GRS track slides easily in the plastic sleeper sections. The brass rail joiners can slide easily also. Making expansion & contraction more of a mobile phenomenon. The stainless steel trial I undertook was less than satisfactory. The single sleepers are tight on the rail & the rail joiners are similarly tight & unyielding. The result can be buckled track when fixed to a plastic base.
On my 24 feet diameter GRS brass track circuit, a couple of minutes track inspection to check track gaps & rail joiner integrity is all that is needed before a running session. I do not recommend the use of stainless steel track with Filcris plastic. It could be a maintenance nightmare as the expansion rates seem incompatible.
I was influenced by use of GRS track after many years of experience of LGB plastic/brass track in the garden.
So far my choice seems to be just fine for me.
No bananas in Derby, sorry to disappoint the sceptics.
Dave
454
Ian,
Sorry, no photos taken and the posts have all now straightened themselves now they are back in the shade!
Dave,
I have decided to keep my posts but only use in semi-shaded areas and beneath large surface boards (i.e. the teminal and junction stations) where any heat will be reflected or dissipated by the track bed.
My posts are 80mmx80mm and black (most smaller sizes sold by Filcris are brown) and the colour probably exacerbated the heat absorption problem.
I need to concrete my posts because it was a struggle, using an auger and a "post hole" lever contraption, to get down just 12 inches (problems with stones/roots/heavy soil) and the pivot mountings of the "Roughneck" hole digger "heavy duty - lifetime guarantee" have bent already (at one stage the pivot bolt flew across the lawn but fortunately had worked loose and not sheared as I first thought)!
Regards,
John.
John,
My posts are brown colour together with the longitudinal stringers.
Now when the posts are in their raw form i.e. in 3 metre lengths for example they are very bendy even when cold.
When propped up against a wall they will not support their own weight. I noticed this after they had been delivered and shared your concern. They are supposed to be flexible that is why they are so useful. However when cut to size & positioned in a purposeful manner i.e. vertical & in the ground supporting the weight of the railway they do their job very well. I think it is to do with loading and the composition of the material. Similarly with the stringers, two stringers held parallel by cube blocks along the length around pre-formed curves is remarkable in it's strength. It is more flexible than timber in this application it scores highly. It seems to retain it's form & can be buried in landscaping without any treatment & forgotten, not like timber. The Filcris website illustrates this and I do not believe it has been misrepresented.
The posts in the ground were easy for me, across the lawn. However, my ground is clay & it was an effort but bashing them in with a big sledge hammer worked. What I realised after when I decided to reposition due to needing bigger radius curve they are very difficult to extract. The easiest way to extract is to find a friendly 4x4 offroader with a high lift jack and use it's 4ton vertical pull. This extraction is more surgically invasive when concreted-in as those who have tried removing concreted-in posts will know very well. So I was pleased that it came out without much ceremony.
My advice for the plastic boards is a separate issue. I made the mistake of using black because it was cheaper. I should in hindsight have used brown boards & paid a bit more. They do absorb a lot of heat in the sunshine & I have noticed that they do expand. That is why I have selected brass rail because that seems to expand also. I do not know what the thermal coefficients of linear expansion are for the respective materials. I do not care about the numbers as I have conducted tests them with (1) :) black plastic & brass rail & (2) :( black plastic & stainless steel. (3) :-\ Not conducted was a similar test using brown board. My assumption would be that brass rail would be ideal & that the brown board would not absorb heat as readily as the black so expansion would be less evident. I leave this for others to report.
A solution to combat the expansion problem as I see it is not to lay full boards longitudinally but to use transverse plank shapes along the stringers. This I have not tried but have seen it later after I had built my circuit.
The service at Filcris was excellent in that they precision cut my boards using CAD & a router producing 20 off with a curved form 9 inches wide with a mid line radius of exactly 12 feet & angled to form an 18 degree profile so a full single track G3 track circle could be laid quite precisely. This aided track laying considerably after the rails had been pre-bent accordingly.
It has been a year now & time will be the judge & jury of this material for our garden railway application.
If bananas appear in my garden, I will be eating them 8)
Dave
454
Spent yesterday afternoon enlarging the post holes to provide footings for brick pillars at one metre intervals across the lawn and mixed 5cwt of concrete to fill the holes.
The pillars (24 inches above lawn level) will be surmounted by dual 4 x 2 timbers (spaced to span the width of the pillars) running the full length of the viaduct. The track will be set between the beams on a base to be located in a manner that will set the railhead below the side beams to assist in restraining derailments.
It is proposed to cast, in resin, simulated plate girder overlays for the timber beams which will "prettify" (is that a word?!) the appearance and increase the height to stop stock falling over the edge.
Definitely "overkill" for the weights it is likely to carry but it should be able to withstand "knocks" from lawn mowers, etc.
John.
P.S. The plastic posts have been relegated to terminus board supports on the North side of the house, where they will be in constant shade!
http://youtu.be/VMtXdoJUJfI
My plastic Gauge 3 railway on much maligned (straight) banana supports that have been just fine in the past few days in the fine sunny weather full sun no shade (East Midlands UK). Never been any signs of banana bending in final installation. Running all day yesterday running many trains with a local visiting member. Gauge 3 GRS brass track on recycled black plastic boards. Notice no sign of over-engineering everything is just minimalistic, non concreted & kept simple, posts driven into lawn. Caravan steps are the climb over solution. King truss girder over garden path is my minimalistic bridge. Tunnel under raised garden shed built on timber decking.
Just a 24 feet diameter circle but great to sit & watch the trains go by during this lovely warm weather with a cold beer on the side 8)
Having fun :)
Dave
454
Cold beer sounds good Dave.
Mark
Just to prove (that after 10 years of planning) something is actually happening!!!
The views are of the brick piers, built yesterday, to carry the high level line across the lawn .... piers are to be rendered in the cool of this evening and painted with Wilko "mid stone" masonry paint.
The brickwork gets almost too hot to touch in the afternoon and had to be constantly "misted" to prevent the mortar drying out while curing (probably accounts for the plastic problem).
The garden looks a bit like a building site at present, with excavations and material for the low level circuit all round.
John.
A couple more pics.
Looks great John, and will be a lovely setting. Does SWMBO know what they are for?
:) Tim
Yes and she helps with the digging and the bricklaying ........ even though the trains don't interest her in the slightest .... oh well, you can't have everything!
John.
Looks good John. So in your case - yes, we have no bananas today. Sorry, couldn't resist that!
Mike
Wow John, those piers, didn't realise HS2 was going your way.
Dave
454
Hello John
Looking good , How deep are the footings below ground ?
John
P.S. The shop is not prepared to stock bricks !
John,
I hope deep enough!
The auger drilled down 14 inches for the plastic post holes, I then enlarged the holes to a square to a depth of around 8ins.
The ground was pummelled and concrete fills the post plugs and the surrounding flat area.
John
Over past five days I have mixed 840 Kg of concrete and mortar and used in excess of 200 bricks (plus a few concrete blocks).
That has provided the supports for only around 45 feet of single line track!
The brick piers have had two layers of cement rendering applied and given a stippled/roughcast finish, ready for coating with Mid-stone masonry paint (if the rain holds off long enough for the rendering to dry out).
More cement, ballast and timber being delivered today.
What at first sight might appear to be a more-or-less level garden turns out to have quite a steep slope across its width. The lowest point is some 28 inches below the highest.... at one point the "low level" double track circuit will be around 30 inches above ground level and the high level line will cross above it at around 40 inches (before descending to a junction between the two and then climbing away again).
Huge lumps of limestone rock and tree/shrub roots are proving main obstacles and are slowing progress.
The house was built for keen gardeners who had a quarry lorry deliver an enormous load from the High Peak... so much that the garden is littered with stuff and they gave a lot way around the village!
It won "Best Garden in the Village" award in those days......not much hope of that any more!
My legacy for future owners will be tons of buried concrete!!
John.
Today (Wednesday) the concrete mixer remained sheeted over (in the expectation of rain....which never came) and my aching back was given a rest.
Nonetheless, yesterday saw more progress and a further three piers were raised and rendered, including the first of two crossings of the low level (twin track circuit) by the high level single track. The total of concrete and mortar mixed to date has now topped 1000 Kilos!
For this latest activity I used "Castle Quickcem" rather than "Blue Circle Ordinary Portland" and this enabled the piers to be constructed and given two coats of render, with a rough cast finish, in under 8 hours. Quickcem costs three times as much as Ordinary Portland but the saving in time is well worth the additional cost.
Downside is you have to work very quickly, since a "mix" remains workable for only 15 minutes but has structural strength in just over an hour.
Photos show the three new piers : The single pier is the last before the track crosses the pond (note large rock moved from where the pier now stands) and the twin structure marks a junction where the high level track splits to form two sides of a triangular junction. Looking through the twin structure, the twin track line curves away along the course roughly marked out by the bricks.
John
This photo shows some of the previously mentioned rocks littered all around the garden which are proving a problem and these are by no means the largest....some weigh well in excess of 100 Kg and have to be levered out and carefully "rolled" ( a job for the "steel toe-capped" boots)!!
Lovely work John, I envy the time you are able to put into it. More power to your elbow and may the good weather continue!
You mention a crossing of the pond and I wonder what span and type of bridge you have in mind? I have presumptiously designed a bridge to span 17 feet across my pond (presumptious because planning approval not yet received). Using a bow-string design constructed from 25mm square hollow section steel, I was pleasantly surprised that it has a predicted load capacity of well above my own weight!
Cheers
Tim 8)
Tim,
I haven't yet resolved the issue of bridges : There are two crossings of the high level line over the low level circuit, as well as two removeable sections to allow access with the mower (one high level, one low level) plus crossing of the pond.
Thankfully, the pond is not very large and the line crosses just the corner and a single span of 8 feet should see it through.
The 40 foot viaduct will (as mentioned in earlier message) be of plate design, and of timber, with resin overlays to represent the plates.
Having just seen the article by Peter Lucas in the Newsletter, I have to admit the plastic drainage channel method has its attractions in terms of simplicity and speed of construction!
Regards,
John.
NOTE: You can follow this project at
http://G3Forum.org.uk/index.php?topic=1099.msg5922#msg5922